Covering the
Construction & Restoring the Road Surface May, 2001 & August, 2001
(Photo: 2Bangkok.com) The road leading up to Ah-saw-mah-tah Intersection
(Photo: 2Bangkok.com)
(Photo: 2Bangkok.com) Workers sweep the dirt off the top of the road-surface
plates before the plates are lifted off by crane and stacked in
the background.
(Photo: 2Bangkok.com)
(Photo: 2Bangkok.com) After the plates are removed, dirt is filled
in the to level of the future road.
(Photo: 2Bangkok.com) August, 2001 - The final road surface slabs
are being poured. Behind this, road drainage pipes are being laid.
At the top of the photo is where the track branches off to go
to the depot and the detour for southbound cars on Ratchapeisek
Road.